Billerica Wastewater Treatment Facility

Treatment Facility and Collection System History:

Construction of the first public system of sanitary sewers and of the treatment plant began in 1966 and was designed to be expandable to meet the growth of the Town of Billerica's population, which was estimated to be 50,000 by the year 2,000.

The original Wastewater Treatment Facility was designed to treat .8MGD (million gallons per day), by using aeration tanks and final settling tanks followed by chlorination before discharge into the Concord River. In 1975 the first upgrade took place which, doubled the aeration tank capacity, added an additional final settling tank and added a sludge disposal building which housed a coil vacuum filter for sludge thickening. This upgrade brought the plant capacity to 1.6 MGD.

In 1982, a return sludge building was added to house the sludge return pumps which had been externally mounted on the final settling tanks.

In 1984, the Town of Billerica's landfill was closed which was where the thickened sludge was disposed of. We began hauling liquid sludge by tanker truck to Greater Lawrence and then to Upper Blackstone Abatement Facility.

In 1988, construction began on the next expansion which would bring the Wastewater Treatment Facility to it=s present size of 5.5 MGD.

New Facilities:

The new facilities include: preliminary treatment (mechanically cleaned bar screens, grit removal equipment); primary treatment (3-60' diameter primary settling tanks, primary sludge pumps, primary scum pumps, primary sludge holding tank); replacement of the mechanical aerators in the aeration tanks with a diffused aeration system; 3-60' diameter final settling tanks; 3 recirculated sludge pumps; secondary scum pump; new chlorination equipment; post-aeration facilities; plant water system improvements; blended sludge holding tank; sludge transfer pumps; new dissolved air flotation thickener; 2-2 meter belt filter presses; associated polymer storage, transfer and conditioning equipment; sludge conveyors; composting facility and storage areas and a new Administration and Maintenance Building, which houses the Plant Superintendent's office, control room, laboratory, personnel facilities, aeration blowers, maintenance shop, garage and emergency generator.

Wastewater Treatment Plant Data

Plant type - Grade 7 secondary Treatment with full composting abilities.
  • Flow - Average daily flow is 3.1 MGD, (includes .40 MGD industrial flow)
  • Designed for 5.5 MGD
  • Plant Lab Results
  • Average BOD5 - In 146, Out 7 Average 95% Removal
  • Average Suspended Solids - In 161, Out 10 Average 94% Removal
  • Collection System - 19 pump Stations with 172 miles of sewers. Additional miles of sewer added yearly.
  • Population Served - 65% of the Town population is sewered.
  • Town Population - 38,000 residents (24,700 residents served)
  • Plant Equipment
  • Mechanical Bar Screen - grit removal - 3 primary clarifiers - diffused air aeration tanks - 6 final clarifiers - chlorine tank - post aeration tank - 3 sludge housing tanks - 2 diffused air flotation thickeners - 2-2 meter belt filter presses - 12 - 200 cubic yard bins - 24,000 square feet uncovered compost storage area.
  • Plant Staff And Licenses
  • Plant Superintendent- (Gr. 7), Grade V Operator- (Gr. 7), Maintenance Supervisor-( Gr. 4.), Lab Technician- (Gr.7), 7 Licensed Operators (1-Gr. 7, 1-Gr.6, 5-Gr.4), 9 Maintenance Men (1- Gr. 7, 1-Gr 4, 2-Gr. 1), Principal Clerk
  • 21 Personnel total, operation is 365 days per year, 24 hour per day , 7 days a week
  • Preliminary Treatment

    Primary Treatment

    Secondary Treatment

    Disinfection

    Post-Aeration

    Sludge Thickening

    Sludge Dewatering

    Sludge Stabilization

    • Aerated Static Pile Composting - sludge cake from the belt filter presses is transferred by conveyors, blended with a bulking agent (wood chips or wood ash) to reduce its moisture content; increase porosity and facilitate materials handling; and is then placed in one of 12 concrete bins. Each bin is loaded to form a pile which is aerated by blowers and perforated piping to enhance aerobic decomposition and stabilization of the sludge.
    • Curing and Storage Area - after the sludge/bulking agent mixture is allowed to actively compost for 14 to 21 days, the material is subsequently stockpiled in the storage areas adjacent to the Composting Building, where it is allowed to cure for an additional time before it is transported offsite for final disposal. The end product may be marketed for beneficial use such as landscaping or conditioning poor quality soils.

    Problems Overcame/Success Achieved:

      In the fall of 1992, the Town of Billerica Wastewater Treatment Facility (WWTF) started experimenting with woodash as a bulking agent instead of wood chips (which has been used in the original start-up). With cooperation of the Odor Control Committee, the WWTF started composting at 50% capacity to show the plant could eliminate odors with a change in the bulking agent. By February of 1993, odor control had been successful and the WWTF started composting at 100% capacity. The WWTF had generated between 6,000 and 8,000 cubic yards of Type I Compost per year since 1993, due to the inception and use of woodash and sawdust as a bulking agent.

    In May of 1997, the Town of Billerica Wastewater Treatment Facility submitted an application to the EPA for the "Beneficial Use of Biosolids Award". This is a ten year old program that recognizes the outstanding efforts to promote the beneficial use of biosolids. The Billerica WWTF won third place and became the only Massachusetts facility to win a National Beneficial Biosolids Award in the history of the program. The award was officially received October 20, 1997 at the EPA Wastewater Management Excellence Ceremony in Chicago by the Superintendent of the Billerica Wastewater Treatment Facility, Arthur Malcuit.



    Contact Information

    Billerica Wastewater Treatment Plant
    70 Letchworth Ave.
    No. Billerica, MA 01862

    Tel. 1-978-671-0956
    Email Bilwwtp@aol.com