Town of South Hadley
Wastewater Treatment Facility   

The Town of South Hadley Wastewater Treatment Facility is located on the eastern bank of the Connecticut River and is situated on land in the City of Chicopee that the Town of South Hadley acquired back in the late 1950’s when the original South Hadley Primary Wastewater Treatment Plant was constructed in 1959. The South Hadley Wastewater Facility is one of many along the Connecticut River responsible for improving water quality to a Class B status. Not only does the river support a healthy aquatic population, a direct result of higher dissolved oxygen levels, several species of birds have been observed by plant personnel including numerous Bald Eagle sightings around the plant. 

Over the last ten years the Town of South Hadley  has made progress addressing and eliminating combined sewer overflows (CSOs).  In the late 1980’s there were thirteen permitted CSOs and by 2001 the number was reduced to only four.  Plant influent flows are now less affected by wet weather or heavy rainfall resulting in more stable plant operations. 

As part of the facilities ongoing commitment to improving process operations, facility management recently presented a field study report at the November  2001 Annual Residuals & Biosolids Conference under New Developments in Management – The Operators Perspective “Long Solids Retention Time Operation”. A copy of this Study is available by contacting the South Hadley Facility at 413-538-5040. The study is summarized below under the heading “Whats New”.        

  Operational Highlights

Start up:  Secondary Facility 1980 

Design Flow : 4.2 MGD     Average Daily Flow: 2.1 MGD 

Population Served:  18,000  including all of South Hadley and portions of the Town of Granby and the City of Chicopee 

Type:  Conventional Activated Sludge    Facility Grade:  6 

Percent Industrial: 5%, with Industrial Pretreatment Program in place. 

System:  75 miles of sewer lines with five pumping stations 

Treatment Processes:  All wastewater is collected at the Main Street pumping station where it travels through either one or two comminutors with a bar rack for backup. The flow is pumped a half mile to the wastewater treatment facility aerated grit chamber (1), low pressure blowers (2), primary clarifiers (3), primary sludge pumps (2), primary scum pumps (2), mechanical aeration tanks (4), autodox dissolved oxygen controller (2), secondary clarifiers (2), return sludge pumps (2), waste  sludge pump (1),  secondary scum pump (1),  chlorine contact tanks (2), chlorine scale/chlorinators (2), gravity thickeners (2), vacuum filter (1), belt press (1), lime silo (1),  plant water pump (1), treated effluent pumps (2), emergency generator (1).  

Mode of Operation:  The secondary wastewater treatment facility has been operated in the conventional activated sludge mode from 1980 up until June of 2000 with a sludge retention time of 4 – 6 days.  In June 2000 the sludge retention time was increased to 35 days in an effort to improve operating efficiency (results are summarized under "What’s New").               

                                                     

Mechanical surface aerators transferring oxygen to the bacteria in the mixed liquor suspended solids averaging 5,000 mg/l with a 16 – 20 hour detention time and an SRT of 35 days.    

Solids Handling: Primary and secondary solids removed from the system are blended in two gravity thickeners. Thickened sludge at 5 % solids concentration is pumped to a two meter belt press and dewatered to 26 – 28 % solids and then transported/incinerated off site by an outside sludge disposal company, Synagro, Inc..  

Odor Control:  Chlorine, potassium permanganate and sodium chlorite are  all used for odor control.  An odor counteractant “Phantom 4” is atomized at the headworks, gravity thickeners and on the belt press during sludge dewatering. 

                                        Peripheral Flow Secondary Clarifier, 75'  diameter 

 

Completed upgrades:  A two meter belt filter press with new sludge pump, pug mill and lime system was installed in 1991;  three old sludge pumps were replaced with new pumps in 1994; the metal/wood primary clarifier components were replaced with new polyurethane collector chains/gears and fiberglass flights in 1998.  Installed two new variable frequency drive controllers for sewage pump motors at the Main Street pumping station in 2001.

Future Upgrades:  In 2001, Tighe & Bond Consulting Engineers worked with Town DPW/Facility personnel and completed a Comprehensive Wastewater Management Plan  outlining a 3-phase program with upgrades to the wastewater collection system, pumping stations and wastewater treatment plant.                             

 

Permit Requirements: BOD and TSS @ 30/30 mg/l, Chlorine Residual 1.0 mg/l, 200 Fecal Coliform/100ml average monthly.  Report only:  TKN; Nitrite + nitrate nitrogen and total phosphorus.  

Average Influent TSS -  300 mg/l Average Effluent TSS -  15 mg/l Average % SS Reduction  95%

Average Influent BOD -  175 mg/l Average Effluent BOD -  5 mg/l Average % BOD Reduction 97%

Staffing: Seven full-time certified employees & one part-time IPP Coordinator. 

CSO Status: Only four remaining CSO’s from a total of 13.  

Safety Program: A Safety Program is in place with monthly meetings/training sessions. 

Standard Operating Procedure (SOP) Program : An ongoing write-up of routine unit operations takes place in order to standardize plant operations. 

What’s New: 

Long Solids Retention Time Operation Field Study : As part of the ongoing process of trying to improve plant operations and reduce costs, a field study was conducted where long solids retention time was adopted  in order to look at reducing secondary solids, improve operations and to reduce operating costs.  The below graph clearly shows the daily reduction in the pounds of waste activated sludge. 


Study Highlights

Chemical Cost Savings 

Town of South Hadley Board of Selectmen 

Department of Public Works Superintendent: Gregory Kereakoglow, P.E. 

Water Pollution Control Supervisor:  Rudolf  F. Urgiel 

South Hadley Water Pollution Control Facility
2 James Street
Chicopee, MA  01020
E-mail:
  rudy.u@the-spa.com
Tel:  413-538-5040
FAX:  413-536-7151


           Homepage